2 X 500 MW NTPL Tuticorin Thermal Power Project, Tuticorin, Tamilnadu-Boiler Package

Scope of Work
Erection, Testing and Commissioning of Boiler Structures, Pressure Parts, Non-Pressure Parts, Rotating Equipments, Etc.

Milestone Schedule
Steel Structure Erection- Jan 2011
Boiler Drum Lifting- 29-Sep-2011
Hydro Test- June 2012
Initial Firing- Oct 2012