Scope of Work
Erection, Testing and Commissioning of Boiler, Turbine, Generator & its Auxiliaries including Electrical and C & I Works.
Milestone Schedule
Unit I
Steel Structure Erection- 13-Dec-2010
Boiler Drum Lifting- 23-May-2011
Hydro Test- 28-Jan-2012
Initial Firing- 12-April 2012
Unit II
Steel Structure Erection- 11-Mar-2011
Boiler Drum Lifting- 12-Aug-2011
Hydro Test- 21-April-2012
Initial Firing- 6-Jul-2012